Existing farm buildings in open countryside, before design work begins
Part 1 of 2

Guide · Process

Your Project, Stage by Stage

From the first meeting to a planning decision: what happens, what you'll receive and what to expect.

Stages 00–03 · For homeowners & self-builders in England · 12 min read

Introduction

Knowing what comes next

A building project is a sequence of decisions, each one building on the last. When you know what happens at each stage, and why, the whole process becomes calmer and more predictable.

This is the first of two guides. It follows a typical project from our first meeting through to a planning decision, set out in the same numbered stages we use in our fee proposals. Part 2 picks up from technical design and follows the project through to completion on site.

Not every project needs every stage. A modest extension moves faster than a new home or a listed building, but the order rarely changes.

Before you start

Three things that shape every project

Budget
Tell us your build budget at the outset. It is the most useful single piece of information we can have, and it shapes every design decision that follows.
Time
Most householder projects take three to six months from first meeting to planning decision. Listed buildings, new homes and sites needing seasonal surveys usually take longer.
Quality
Historic buildings, conservation areas and sensitive rural sites call for better materials and more detailed drawings from the start, and more people involved in the decision.

In this guide

The stages at a glance

  1. 00Initial meeting & appointmentYour ideas, the site's potential and a written fee proposal.View
  2. 01Survey & briefAccurate drawings of what's there now, and an agreed brief.View
  3. 02Concept designDesign options, refined together until they’re right.View
  4. 03Planning & Listed Building ConsentThe application, the reports it needs, and the decision.View
  5. £Costs & your route to a builderChecking the budget and choosing how to appoint a builder.View
00

Stage 00

Initial meeting & appointment

We meet at your property or on the site to walk round, listen to what you'd like to achieve and look at what the building or plot allows. We'll talk through likely planning constraints, the approvals you'll need, any obvious risks and a realistic build budget.

Afterwards we write to you with a fee proposal. It sets out the stages we'd look after, what is included in each and a lump-sum fee for each stage, so you know where you stand before anything is committed.

Your appointment

When you're ready to go ahead, we confirm the appointment in writing: the fee proposal together with our terms of engagement. Work starts once both are agreed. A clear written appointment protects you as much as it protects us.

Health & safety duties

Under the Construction (Design and Management) Regulations 2015, anyone commissioning building work has legal duties, including passing on information you hold about the property, such as asbestos surveys, drainage records or details of past alterations. For homeowners, most of these duties are normally carried out by the contractor or principal designer. We'll explain what applies to your project at the outset.

Talking a project through on site
Talking it through on site
You'll receive
A written fee proposal and terms of engagement.
We'll need from you
Your ideas and budget, plus any documents you hold: title plan, previous planning decisions, surveys.
Typical timescale
One to two weeks from meeting to fee proposal.
01

Stage 01

Survey & brief

Everything that follows is only as good as the information it's built on, so we begin with an accurate measured survey. We record the floor plans, elevations, roof and site, and draw up the building as it exists: plans and elevations at 1:100, with a location plan and block plan for the planning application.

On older buildings the survey is also a chance to read the building: how it has changed over time, which parts are original and which are later additions, where openings have been blocked up. That understanding feeds directly into the design, and often reveals opportunities that aren't obvious at first.

Where the work involves changes in level, trees, boundaries or a larger site, a separate topographical survey by a specialist surveyor is usually needed. We'll tell you if it is and help you get quotes.

We also use this stage to firm up the brief: the rooms and spaces you need, how you live day to day, what you'd like to keep and what matters most.

Aerial view of an existing site in a market town
Recording the existing site
You'll receive
Measured drawings of the existing building and an agreed written brief.
We'll need from you
Access to every room, the loft and the garden.
Typical timescale
A survey visit of half a day to a day; drawings within two to three weeks.
02

Stage 02

Concept design

With the building understood, we develop design options, usually several different ways the space could work. We talk them through with you, then refine the preferred approach until it's right.

Concept drawings deal with layout, scale and appearance: floor plans, elevations and, where it helps, sketches or 3D views. They show what the council needs to see. How it will be built comes later. Structure, construction details, kitchens and services are resolved at Stage 04.

Pre-application advice: only on some projects

Pre-application advice isn’t needed on every project. We recommend it project by project, where an early view from the council is worth the extra time and fee, and we’ll explain why. If you go ahead, we send outline drawings and a short description, and the case officer replies in writing, sometimes after a site meeting. Councils charge for this, and replies can take several weeks.

It is usually worth it for:

  • A listed building, or work in a conservation area.
  • A new home in the countryside or on the edge of a village.
  • A barn or farm building conversion.
  • A site that has been refused before, or a design that goes beyond what local policy usually allows.

It is usually not needed for a straightforward single-storey rear extension, or a design that clearly follows the council’s own guidance. There it adds time and cost without much benefit, and we go straight to the application.

The key idea

Changes are cheapest on paper, and cheapest of all at concept stage. This is the time to test ideas, ask questions and change your mind.

Proposed ground floor plan
Proposed ground floor · Isham Farm
You'll receive
Design options, then a developed concept design.
We'll need from you
Clear feedback on each round, and a decision on the preferred option.
Typical timescale
Four to eight weeks, depending on the rounds of revision. Allow extra time where pre-application advice is recommended.
03

Stage 03

Planning & Listed Building Consent

Once the design is agreed, we prepare the full application: planning drawings, application forms and the supporting statements the council requires. We submit it as your agent and deal with the council on your behalf throughout, responding to queries and negotiating amendments where needed.

Which consent?

  • Householder planning permission: extensions and alterations to a house.
  • Full planning permission: new homes, conversions and changes of use.
  • Listed Building Consent: needed for almost any alteration to a listed building, inside or out, often alongside planning permission.
  • Prior approval or a Lawful Development Certificate: where the work may fall within permitted development, including Class Q barn conversions and larger rear extensions.

Reports your application may need

Depending on the site, the council may ask for specialist reports. Commissioning them early avoids delays at validation.

Heritage statement
For listed buildings and conservation areas. Explains the significance of the building and the effect of the proposals.
Ecology & bat survey
Often needed for barns, roof spaces and older buildings. Some surveys can only be carried out between May and September, so timing matters.
Arboricultural report
Where trees stand on or close to the work.
Flood risk assessment
For sites within a flood zone.
Biodiversity net gain
Required for most new homes and other non-householder applications. Householder extensions are exempt.
Others
Highways, drainage, archaeology, contamination or noise, as the site requires.

The application journey

  1. Submission

    We submit the application through the Planning Portal and pay the council's fee on your behalf.

  2. Validation

    The council checks everything required is included, usually within one to two weeks.

  3. Consultation

    Neighbours, the parish council and consultees have at least 21 days to comment.

  4. Assessment

    The case officer weighs the proposal against policy and may ask for amendments. We handle the negotiation.

  5. Decision

    The target is eight weeks from validation for householder and minor applications, and thirteen for major ones. Extensions of time are common.

Planning visualisation of new homes arranged around a farmyard
Planning visualisation · The Old Farm Yard

Planning drawings are not construction drawings

A planning approval confirms what you can build, not how to build it. Your builder will need the technical drawings and specification prepared at Stage 04 before they can price accurately and start work.

After the decision

Planning permission normally lasts three years. Most approvals come with conditions, and some must be discharged (details approved by the council) before any work starts, such as materials samples, drainage or ecology measures. We'll help you work through them.

Where a new home is involved, check the Community Infrastructure Levy early. Self-build relief has to be claimed and approved before work begins; it can't be claimed afterwards.

You'll receive
Planning drawings, the submitted application and the decision notice.
We'll need from you
Sign-off on the drawings and the council's application fee.
Typical timescale
Two to four weeks to prepare; around eight weeks for a decision once validated.
£

Before Stage 04

Costs & your route to a builder

With planning in hand, it's time to test the budget and decide how you'll appoint a builder. The answer shapes how much technical information Stage 04 needs to produce.

Negotiated

Work with one builder from early on

Competitive tender

Three or more builders price the same package

Negotiated. Common on home projects, particularly when you already know or have been recommended a builder you trust. The builder can give early cost advice, suggest practical ways of building and start sooner, and the drawings can focus on what they actually need. What you give up is a direct comparison, which is where an independent cost check earns its keep.

Competitive tender. A full technical package goes to three or four builders to price on the same basis, so quotes can be compared like for like. It's the usual route for larger projects, grant-funded work and commercial schemes. It needs more detailed information up front. The lowest price is not always the best value, because gaps in the information tend to come back as extras on site.

Cost advice

On larger or more complex projects we recommend a quantity surveyor to prepare a cost plan: an itemised estimate that shows what each part of the work costs, so items can be added or omitted before you commit. On smaller projects, a trusted builder's estimate can serve the same purpose.

The key idea

Check the budget before technical design begins. It is far easier to adjust the scope now than once detailed drawings are complete.

This guide is general information for projects in England and is not legal, planning or financial advice. Timescales are typical rather than guaranteed, and rules change. Every project is different, so please ask us about yours.